Item A—Minutes of June 17, 2020 Citizens Oversight Committee Regular Meeting
Item B—MERA Governing Board Response to COC Informational Requests Re: Next Gen Project Implementation Agreement and It’s Termination (distributed 9-15-20)
Item C—Update on Status of Next Gen System Project and Budget
* Next Gen Project Staffing
* Customer Design Review
* Construction Schedule, Cost Estimates and Bid Packages
* Project Budget
C-1—MERA Project Budget and Expenditures Summary, 09/08/2020
Item E—Review of Funds 70038 and 70039 – Next Gen Project Revenues and Expenditures
* FY19-20 June 9, 2020 – June 30, 2020 as of September 14, 2020 (distributed 9-15-20)